Joined
·
5,307 Posts
A few things:
-First all strands need to be equal tension during the build.
-Twist string to length prior to serving. A string with a lot of twist is more stable.
-Mark certer of strand bundles for peep installation during build.
-Have a LOT of tension on the string when serving. If your server is causing the string to twist during application, you will end up with some movement..
-First all strands need to be equal tension during the build.
-Twist string to length prior to serving. A string with a lot of twist is more stable.
-Mark certer of strand bundles for peep installation during build.
-Have a LOT of tension on the string when serving. If your server is causing the string to twist during application, you will end up with some movement..